Project | Refrigeration installations |
Duration | Approx. 18 months |
Material | 1.4301, S235, 16Mo3 |
Number of welds | Approx. 5000 welds |
Dimensions | DN60, DN80, DN120 – DN600 |
Technical floors – Installed with steel structures to ensure stability and safe maintenance.
Materials and execution – Steel pipes with thermal insulation and anti-corrosion protection have been used, with flanged connections for easy servicing.
Reliable system operation – Fans, chillers, pumps, and manifolds have been installed and connected into an energy-efficient and safe heating and cooling system.