Project | AD Blue Supply and fuel pipelines |
Duration | Approx. 5 months |
Material | 1.4301 stainless steel |
Number of welds | Approx. 600 welds |
Dimensions | DN15 – DN50 |
Stainless steel installation
A stainless steel installation has been completed on the project, featuring high-quality flanged connections and orbital welding. Electromotorized valves and fittings have been installed for reliable automation and precise flow control. Pipelines are neatly mounted on supporting structures with anti-vibration protection, ensuring long-lasting and safe system operation.