Projekt: Neubau Zentralklinikum Lörrach

Project heating installation
Duration Approx. 3 Years
Material 1.4301, S235, 16Mo3
Number of welds Approx. 3500 welds
Dimensions DN60, DN80, DN120

The Zentralklinikum project in Lörrach involves the complex installation of all key systems for heating, ventilation, air conditioning, plumbing, and drainage. Pre-insulated steel pipes are used for the heating system, while stainless steel and copper pipes are utilized for the transport of medical gases, such as oxygen and nitrous oxide. The ventilation system includes galvanized and steel pipes to ensure optimal air distribution throughout the building.

The Zentralklinikum project covers over 89,600 m² of gross floor area, with 2,400 rooms, including 430 technical rooms, ensuring high energy efficiency and safety of all installations.

The building is designed to optimize all operational processes, and with the help of advanced systems, Zentralklinikum will provide high-quality healthcare and a comfortable environment for both patients and staff.