Projekt: Electrical Installation
The scope of installation includes: The wiring harnesses are routed through predefined cable ducts and junction boxes, with each connection subjected to continuity and insulation

Projekt: Carl Zeiss Jena
Project Refrigeration installations Duration Approx. 18 months Material 1.4301, S235, 16Mo3 Number of welds Approx. 5000 welds Dimensions DN60, DN80, DN120 – DN600 Technical floors

Projekt: Carl Zeiss Berlin
Project Refrigeration installations Duration Approx. 6 months Material S235 Number of welds Approx. 500 welds Dimensions DN60, DN80, DN120 High-quality rooftop installation – Zeiss Steel

Projekt: Audi Formula Racing
Project AD Blue Supply and fuel pipelines Duration Approx. 5 months Material 1.4301 stainless steel Number of welds Approx. 600 welds Dimensions DN15 – DN50

Projekt: Universitätsklinikum Münster (UKM)
Project heating installation Duration Approx. 11 months Material 1.4301, S235, 16Mo3 Number of welds Approx. 4 000 welds Dimensions DN60 – DN500 The construction and

Projekt: Neubau Zentralklinikum Lörrach
Project heating installation Duration Approx. 3 Years Material 1.4301, S235, 16Mo3 Number of welds Approx. 3500 welds Dimensions DN60, DN80, DN120 The Zentralklinikum project in

Project Berief food in Beckum, Germany
We completed the project of the food industry plant in Germany.